Fitness Center
A complicated geometry of hips and valleys made this a challenging project for our drafting department. Creating a 3D model of the entire framing ensured that every piece of steel fit to amazing precision.
The site conditions created another challenge for us. A small jobsite with limited storage space, an adjacent building open for public use and large components for the roof trusses required deliveries be carefully coordinated and well planned. The configuration of the roof framing required two cranes. While one crane held the main truss in position the second crane placed the adjoining trusses stabilizing the entire system.
The job was completed on time with a high level of safety and no incidents or accidents.