Lourdes High School Addition

The largest challenge of this jobsite was the front auditorium which was built in the shape of a cone.

This project consisted of 68 tons of structural steel and 52 tons of steel joists. Not only did this project occur during the school year while classes were in session, but was in a residential area which limited delivery times and storage space. This required sensitive sequencing and careful coordination of installation. The largest challenge of this jobsite was the front auditorium which was built in the shape of a cone. This presented difficulty in the drafting, fabricating and the installation of the roof framing system.